Week of 3/3 – 3/7
- Work hours: 7:00 a.m. - 3:30 p.m.
- Continue installing light pole bases, conduits, and pull boxes from Hebron St. to Harvard St.
- Continue paving temporary sidewalks after conduit installation work
- No drainage structures are expected to be installed this week
Week of 3/10 – 3/14
- Work hours: 7:00 a.m. - 3:30 p.m.
- Finish installing light pole bases, conduits, and pull boxes from Hebron. to Harvard St
- Start installing conduits from Wood Ave to Itasca St
- Continue paving temporary sidewalks after conduit installation work
Week of 3/17 – 3/21
- Work hours: 7:00 a.m. - 3:30 p.m.
- Continue installing conduits from Wood Ave to Itasca St
- Continue paving temporary sidewalks after conduit installation work
Week of 3/24 – 3/28
- Work hours: 7:00 a.m. - 3:30 p.m.
- Continue installing conduits from Wood Ave to Itasca St
- Continue paving temporary sidewalks after conduit installation work
- Tentatively begin the installation of remaining drainage structures at Tampa St and between Kennebec St. and Hebron St.
*Please note the nature of this construction work is weather dependent.