Friday, March 7, 2025

Cummins Highway Construction Update: March 2025


Week of 3/3 – 3/7
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Continue installing light pole bases, conduits, and pull boxes from Hebron St. to Harvard St.
  • Continue paving temporary sidewalks after conduit installation work
  • No drainage structures are expected to be installed this week
Week of 3/10 – 3/14
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Finish installing light pole bases, conduits, and pull boxes from Hebron. to Harvard St
  • Start installing conduits from Wood Ave to Itasca St
  • Continue paving temporary sidewalks after conduit installation work
Week of 3/17 – 3/21
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Continue installing conduits from Wood Ave to Itasca St
  • Continue paving temporary sidewalks after conduit installation work
Week of 3/24 – 3/28
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Continue installing conduits from Wood Ave to Itasca St
  • Continue paving temporary sidewalks after conduit installation work
  • Tentatively begin the installation of remaining drainage structures at Tampa St and between Kennebec St. and Hebron St. 

*Please note the nature of this construction work is weather dependent.

No comments:

Post a Comment